Project Management: Estimating Project Times and Costs

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/25

flashcard set

Earn XP

Description and Tags

A comprehensive vocabulary flashcard set covering estimating fundamentals, top-down, bottom-up, and hybrid techniques, influencing factors, and cost categories in project management.

26 Terms

1
New cards

Estimating

The process of forecasting or approximating the time and cost of completing project deliverables.

2
New cards

Top-Down Estimates

Estimates usually performed by senior management that derive project duration and cost from analogy, group consensus, or mathematical relationships.

3
New cards

Bottom-Up Estimates

Estimates typically performed by the people doing the work, based on individual elements found in the work breakdown structure (WBS).

4
New cards

Planning Horizon

An estimating factor where time and cost estimate accuracy improves as individual work packages are defined, whereas long-duration projects increase uncertainty.

5
New cards

Project Complexity

An estimating factor where time to implement new technology expands nonlinearly, and poorly written scope specifications lead to estimating errors.

6
New cards

People

The accuracy of estimates depends on the skills of the people making the estimates. How familiar are they with the task they are estimating?

7
New cards

Structure and Organization

The speed gained from concentrated focus and localized project decisions. This speed comes at an additional cost of tying up personnel full time. Projects operating in a matrix environment may reduce costs by more efficiently sharing personnel across projects but may take longer to complete since attention is divided and coordination demands are higher.

8
New cards

Padding Estimates

The practice of adding extra time and cost to an estimate to reduce the risk of being late, which can compound across project levels and seriously overstate total project duration and cost.

9
New cards

Organization Culture

An organizational factor reflecting differing internal beliefs on estimates, ranging from viewing detailed estimating as not worth the effort to viewing accurate estimates as the bedrock of effective project management.

10
New cards

Responsibility Guideline

The estimating guideline stating that work package estimates should be made by the person(s) most familiar with the task based on experience and best judgment.

11
New cards

Crowdsourcing (Estimating)

The practice of using several people with relevant experience and knowledge of a task to produce more reasonable and realistic cost or time estimates.

12
New cards

Normal Conditions

The baseline estimating assumption that tasks are conducted under standard project conditions using efficient methods and a normal level of resources.

13
New cards

Time Units Guideline

The guideline requiring consistent, specific units of time (such as workdays, workweeks, or calendar days) to be selected early in the development phase of the project network.

14
New cards

Independence Guideline

The estimating guideline directing estimators to treat each work package task as independent of other tasks rather than aggregating tasks or forcing them to fit a predetermined total.

15
New cards

Contingencies Guideline

The guideline stating that individual work package estimates should not include extra allowances; instead, top management establishes a separate contingency fund to cover unforeseen events.

16
New cards

Consensus Methods

A top-down estimating method that uses the pooled experience of senior and middle managers through discussion and debate to reach a collective best-guess estimate for project duration and cost.

17
New cards

Ratio Methods

Top-down approaches (sometimes called parametric) often used in the concept or 'need' phase that employ ratios or surrogates to develop initial duration and cost estimates.

18
New cards

Apportion Methods

A top-down estimating method used when projects closely follow past projects in features and costs, allocating percentages of total project cost down to specific work breakdown structure tasks.

19
New cards

Learning Curves

A top-down estimating phenomenon recognizing that the time needed to perform a task decreases with repetition, particularly in labor-intensive tasks.

20
New cards

Template Methods

A bottom-up estimating method that uses the actual times and costs of past similar projects as a baseline, adjusting them to reflect differences in the new project.

21
New cards

Parametric Procedures (Bottom-Up)

A bottom-up estimating technique that applies specific quantitative ratios or parameters (such as cost per square foot) directly to individual tasks.

22
New cards

Range Estimating

A bottom-up estimating approach best applied to work packages with significant uncertainty, establishing low, average, and high estimates to evaluate range and risk.

23
New cards

Phase Estimating

A hybrid estimating method used under high uncertainty that begins with an overall top-down macro estimate and develops detailed bottom-up estimates phase by phase as the project progresses.

24
New cards

Direct Cost

A project cost that is clearly and directly chargeable to a specific work package.

25
New cards

Direct Overhead

Project costs that closely pinpoint which specific resources are being used in the project.

26
New cards

G&A Overhead

General and administrative organization costs that are not directly linked to a specific project.