Material Price
MATERIAL PRICE: (STANDARD PRICE - ACTUAL PRICE) X ACTUAL QUANTITY PURCHASED
Material Usage
MATERIAL USAGE (EFFICIENCY): (QUANTITY REQUIRED – ACTUAL QUANTITY) X STANDARD PRICE
Unit level material
: (Actual quantity used/number of units produced) – standard quantity required. X units produced
Labour Price
(STANDARD RATE – ACTUAL RATE) X ACTUAL HOURS WORKED
Labour Rate Variance (Efficiency)
(STANDARD LABOUR HOURS – ACTUAL LABOUR HOURS) X STANDARD RATE
Unit level Labour
Actual labour hours used/ number of units produced) – standard labour usage per hour. X units produced
Variable overhead variance price
VARIABLE OVERHEAD VARIANCE PRICE: (BUDGET VARIABLE OVERHEAD FIGURE – ACTUAL VARIABLE OVERHEAD FIGURE) X ACTUAL USAGE
Variance overhead variance usage (efficiency)
(STANDARD OUTPUT – ACTUAL OUTPUT) X STANDARD RATE
Unit level var overhead
(Actual overhead variable total/number of units produced) – standard variable overhead usage. X units produced